Demolitions - Control and Advice

If you want to demolish a building, you will need to let us know six weeks prior to work starting.

Dangerous Structure

You should fill in our online Demolition Notice Form, or otherwise submit your intention in writing to the Building Control Department. This notice must be submitted at least six weeks prior to the proposed demolition. Failure to do so is a contravention of the Building Act 1984 and may result in prosecution.

A location plan of the building and adjoining streets must be provided together with a method statement for the demolition of larger buildings.

Statutory undertakers (gas, electric, water, telecoms and highways) should also be notified in order that they may arrange for their services to be properly sealed.